Summary
The council approved a revised application for a $45 million low-interest state revolving fund loan to fund a consent-decree-required wastewater storage tank project on North Elkhorn.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 13, 2026.
Impact analysis
The low-interest loan funds a federally mandated sewer project; debt service will affect utility rates over time.
Residents served by the sanitary sewer system, through required consent decree compliance.
Mentions & discussions (3)
Urban County Council Ad Valorem 1st Reading — August 13, 2026
The council approved a revised application for a $45 million low-interest state revolving fund loan to fund a consent-decree-required wastewater storage tank project on North Elkhorn.
Urban County Council Work Session Packet — August 11, 2026
The KIA loan for the North Elkhorn wet weather storage tank grew from $20 million to $45 million toward a roughly $53 million consent decree project near Hamburg — a 2% loan requiring no principal payments until construction is done.
Urban County Council Work Session Packet — January 20, 2026
The council docketed a $1.495 million design contract for a new pump station required under the federal sewer consent decree.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lexington
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.