The new senior center is on track to open early this fall and is under budget, though two change orders added about $106,000 for Shillito Park road paving assessments and accessibility improvements.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 24, 2026.
Impact analysis
Change orders raised the architect contract to $1,085,750 and Terracon's to $64,175, but the overall project remains under budget.
Lexington seniors will get a new therapeutic recreation center with improved accessible parking and roads.